New electrical service

Joined
Apr 2, 2015
Messages
84
Reaction score
8
Started work on my new electrical service . Meter base mounted SERVICE MAST INSTALLED AND CUT OFF .

Could not find my weather head . Slipped the service jack down over the conduit , but have not " dryed it in " with screws and black asphalt "pooky " .

Next I need to install the cables / wires up the mast and cap the mast with a weather head .

Then drive a ground rod and run the ground wire .

God bless
Wyr
 

Attachments

  • Like
Reactions: Ian
Joined
Apr 2, 2015
Messages
84
Reaction score
8
Received a green tag (m passed inspection ) , yesterday .

Depending on weather , plan to get the power compant to hook it up and atart taking down the old stuffm and replacing it .

God bless
Wyr
 

Attachments

  • Like
Reactions: Ian
Joined
Apr 2, 2015
Messages
84
Reaction score
8
New meter base hot , removed old meter base , 2 two circuit boxes . patched sheet metal and caulk / paint .

Got the rain tight load center installed and hot . Temporarily tied in the cable to dryer and water heater .

Permanently tied in the kitchen loadcenter on the opposite side of the wall .

God bless
Wyr
 

Attachments

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Members online

No members online now.

Forum statistics

Threads
128,920
Messages
1,266,502
Members
10,644
Latest member
rapid

Latest Threads

Top